The correct answer is B: Risk response strategies and risk analysis. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?

Options

  • ARisk reserve analysis and risk thresholds
  • BRisk response strategies and risk analysis
  • CRisk reviews and risk register analysis
  • DRisk assessments and risk audits

Topics

#Control Risk Process#Risk Monitoring#Risk Documentation Updates#Risk Analysis