PMI-RMP Question #376: Real Exam Question with Answer & Explanation
The correct answer is B: Risk response strategies and risk analysis. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?
Options
- ARisk reserve analysis and risk thresholds
- BRisk response strategies and risk analysis
- CRisk reviews and risk register analysis
- DRisk assessments and risk audits
Topics
#Control Risk Process#Risk Monitoring#Risk Documentation Updates#Risk Analysis