As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?

The correct answer is B. Risk response strategies and risk analysis. The Control Risk process (called 'Monitor Risks' in PMBOK 6th edition) is the ongoing process of implementing agreed-upon risk response plans, tracking identified risks, identifying new risks, and evaluating overall risk process effectiveness. When updating risk documents, the pr

Risk Monitoring and Reporting

Question

As a result of the Control Risk process, the project manager updates the project risk documents using outcomes from which of the following?

Options

  • ARisk reserve analysis and risk thresholds
  • BRisk response strategies and risk analysis
  • CRisk reviews and risk register analysis
  • DRisk assessments and risk audits

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    89% (31)
  • C
    3% (1)
  • D
    3% (1)

Explanation

The Control Risk process (called 'Monitor Risks' in PMBOK 6th edition) is the ongoing process of implementing agreed-upon risk response plans, tracking identified risks, identifying new risks, and evaluating overall risk process effectiveness. When updating risk documents, the project manager draws on: (1) risk response strategies - to document whether planned responses were executed and whether they were effective, and (2) risk analysis - to reflect updated probability and impact assessments based on current project performance data. Option A (risk reserve analysis and thresholds) are inputs to risk planning, not primary update drivers. Option C (risk reviews and register analysis) is a subset process, not the full source of updates. Option D (assessments and audits) are techniques within the process, but the outputs that feed document updates are specifically the analysis results and strategy execution outcomes described in Option B.

Topics

#Control Risk Process#Risk Monitoring#Risk Documentation Updates#Risk Analysis