PMIPMI
PMI-RMP · Question #375
PMI-RMP Question #375: Real Exam Question with Answer & Explanation
The correct answer is A: Scheduled, budgeted, and easy for project stakeholders to understand. See the full explanation below for the reasoning.
Stakeholder Engagement
Question
The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be which of the following?
Options
- AScheduled, budgeted, and easy for project stakeholders to understand
- BCost-effective, validated by Monte Carlo analysis, and assigned
- CIterative, scaled to the project, and addressing threats and opportunities
- DTimely, cost-effective, agreed-upon, and accepted
Topics
#Risk response planning#Stakeholder agreement#Risk response implementation#Actionable risk responses
Community Discussion
No community discussion yet for this question.