nerdexam
PMIPMI

PMI-RMP · Question #375

PMI-RMP Question #375: Real Exam Question with Answer & Explanation

The correct answer is A: Scheduled, budgeted, and easy for project stakeholders to understand. See the full explanation below for the reasoning.

Stakeholder Engagement

Question

The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be which of the following?

Options

  • AScheduled, budgeted, and easy for project stakeholders to understand
  • BCost-effective, validated by Monte Carlo analysis, and assigned
  • CIterative, scaled to the project, and addressing threats and opportunities
  • DTimely, cost-effective, agreed-upon, and accepted

Topics

#Risk response planning#Stakeholder agreement#Risk response implementation#Actionable risk responses

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions