nerdexam
PMIPMI

PMI-RMP · Question #364

PMI-RMP Question #364: Real Exam Question with Answer & Explanation

The correct answer is A: Increase the risk manager's position to a full-time position and acquire a dedicated project. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

A six-month, US$1,2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones. Based on this project data, what technique should the risk manager recommend to improve the risk management process?

Options

  • AIncrease the risk manager's position to a full-time position and acquire a dedicated project
  • BAdjust project risk thresholds to increase the number of residual risks on the project.
  • CIncrease the frequency of risk status meetings and update the risk management plan.
  • DPerform a variance analysis and potentially allocate more reserves to improve risk mitigation.

Topics

#Risk Process Improvement#Risk Response Monitoring#Resource Allocation#Risk Manager Role

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions