PMI-RMP · Question #364
A six-month, US$1,2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the proj
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #364. The question stem and answer options stay visible for context.
Question
A six-month, US$1,2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones. Based on this project data, what technique should the risk manager recommend to improve the risk management process?
Options
- AIncrease the risk manager's position to a full-time position and acquire a dedicated project
- BAdjust project risk thresholds to increase the number of residual risks on the project.
- CIncrease the frequency of risk status meetings and update the risk management plan.
- DPerform a variance analysis and potentially allocate more reserves to improve risk mitigation.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.