nerdexam
PMIPMI

PMI-RMP · Question #365

PMI-RMP Question #365: Real Exam Question with Answer & Explanation

The correct answer is B: Risk breakdown structure. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?

Options

  • AWork breakdown structure
  • BRisk breakdown structure
  • CCritical path method
  • DOrganizational breakdown structure

Topics

#Risk Monitoring and Reporting#Risk Breakdown Structure (RBS)#Schedule Metrics#Risk Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions