PMI-RMP · Question #365
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
The correct answer is B. Risk breakdown structure. The Risk Breakdown Structure (RBS) is a hierarchical categorization of risks by type or source, and it serves as an input into schedule metrics during monitoring and reporting because it provides the framework to track which risk categories are impacting schedule performance…
Question
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?
Options
- AWork breakdown structure
- BRisk breakdown structure
- CCritical path method
- DOrganizational breakdown structure
How the community answered
(39 responses)- B92% (36)
- C3% (1)
- D5% (2)
Explanation
The Risk Breakdown Structure (RBS) is a hierarchical categorization of risks by type or source, and it serves as an input into schedule metrics during monitoring and reporting because it provides the framework to track which risk categories are impacting schedule performance. The WBS (A) defines project scope, not risk categories. The Critical Path Method (C) is a scheduling technique, not an input document. The Organizational Breakdown Structure (D) maps resources to organizational units, which is unrelated to schedule risk metrics.
Topics