PMI-RMP · Question #394
Which tool can the project risk manager utilize to help identify and assess project risks?
The correct answer is B. Risk surveys. Risk surveys are a structured tool used to gather input from a broad range of stakeholders to identify and assess project risks. They allow the risk manager to collect diverse perspectives efficiently. Risk audits (A) evaluate the effectiveness of the risk management process afte
Question
Which tool can the project risk manager utilize to help identify and assess project risks?
Options
- ARisk audit
- BRisk surveys
- CRisk manager interviews
- DRisk sensitivity surveys
How the community answered
(43 responses)- A2% (1)
- B88% (38)
- C2% (1)
- D7% (3)
Explanation
Risk surveys are a structured tool used to gather input from a broad range of stakeholders to identify and assess project risks. They allow the risk manager to collect diverse perspectives efficiently. Risk audits (A) evaluate the effectiveness of the risk management process after the fact-they do not identify risks. 'Risk manager interviews' (C) is not a standard tool. 'Risk sensitivity surveys' (D) is not a recognized term in standard project risk management frameworks.