PMI-RMP · Question #369

Which of the following is the primary project artifact used to capture risks, strategies, ownership patterns, and other vital information about an organization's project risk baseline?

The correct answer is B. Risk register. The risk register is the central, living document that captures all identified risks, their probability and impact assessments, assigned owners, chosen response strategies (avoid, mitigate, transfer, accept), trigger conditions, and current status. It forms the project's risk bas

Risk Process Facilitation

Question

Which of the following is the primary project artifact used to capture risks, strategies, ownership patterns, and other vital information about an organization's project risk baseline?

Options

  • ARisk action plan with owners
  • BRisk register
  • CMitigation plan
  • DRisk management plan

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    89% (39)
  • C
    2% (1)
  • D
    2% (1)

Explanation

The risk register is the central, living document that captures all identified risks, their probability and impact assessments, assigned owners, chosen response strategies (avoid, mitigate, transfer, accept), trigger conditions, and current status. It forms the project's risk baseline and is continuously updated throughout the project lifecycle. The risk management plan (D) describes the process and methodology but does not contain the actual risk data. A mitigation plan (C) covers only threat responses. A risk action plan with owners (A) is a subset of what the register captures and is not the primary artifact.

Topics

#Risk Register#Project Artifacts#Risk Information Management#Risk Baseline

Community Discussion

No community discussion yet for this question.