PMI-RMP · Question #324
PMI-RMP Question #324: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #324. The question stem and answer options stay visible for context.
Question
At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project. Based on this information, what risk management process improvement should the risk manager recommend for future similar projects?
Options
- AIncrease frequency of risk management meetings with the project manager.
- BRevise the level of accuracy of probability and impact scores.
- CDocument the risk audit report and capture it in the lessons learned database.
- DExpand the use of risk identification techniques.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.