PMI-RMP · Question #326
PMI-RMP Question #326: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #326. The question stem and answer options stay visible for context.
Question
A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead is identifying the most critical information to be presented at an executive level. The information must balance communicating essential information with actions and recommendations. What risk information should be communicated to the project sponsor?
Options
- ASignificant risks and issues and their planned responses
- BRisk matrix showing the distribution of high, medium, and low risks
- CResults of the last project risk brainstorming session
- DSummary feedback from the previous risk audit
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.