PMI-RMP · Question #347
PMI-RMP Question #347: Real Exam Question with Answer & Explanation
The correct answer is B: Risk management methodology, risk management organization, and thresholds and. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
What items should be included in a complex project's risk management plan?
Options
- ARisk management methodology, scope statement, and thresholds and corresponding definitions.
- BRisk management methodology, risk management organization, and thresholds and
- CRisk management organization, templates, and milestone plan
- DRisk management organization, risk communication plan, and milestone plan
Topics
#Risk Management Plan#Plan components#Risk planning#Risk methodology