nerdexam
PMIPMI

PMI-RMP · Question #302

PMI-RMP Question #302: Real Exam Question with Answer & Explanation

The correct answer is C: Planning Process. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

The risk manager wants to determine what is to be measured, how it is to be measured, and what project outcomes are to be measured. In which of the following processes should this be established?

Options

  • AInitiating Process
  • BExecuting Process
  • CPlanning Process
  • DMonitoring and Controlling Process

Topics

#Risk Management Planning#Risk Measurement#Project Management Processes#Risk Metrics

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions