nerdexam
PMI

PMI-RMP · Question #332

The risk management process can be defined as which of the following?

The correct answer is C. Iterative throughout the entire project. Risk management is an iterative process applied throughout the entire project life cycle because new risks can emerge and existing risks evolve at any stage from initiation through closure.

Risk Strategy and Planning

Question

The risk management process can be defined as which of the following?

Options

  • AIterative through the planning phase
  • BBaselined at the beginning of execution
  • CIterative throughout the entire project
  • DUpdated in the execution phase

How the community answered

(21 responses)
  • A
    10% (2)
  • C
    86% (18)
  • D
    5% (1)

Why each option

Risk management is an iterative process applied throughout the entire project life cycle because new risks can emerge and existing risks evolve at any stage from initiation through closure.

AIterative through the planning phase

Limiting risk management iteration to only the planning phase ignores that risks arise and change substantially during execution, monitoring and controlling, and closing phases where ongoing risk management is equally critical.

BBaselined at the beginning of execution

Baselining risk management at the beginning of execution implies it becomes static after that point, which contradicts the dynamic and continuously evolving nature of project risk throughout its life cycle.

CIterative throughout the entire projectCorrect

Risk management is iterative throughout the entire project because new risks emerge during execution and monitoring, previously identified risks change in probability or impact, and risk responses must be continuously evaluated and updated from project initiation through closure to maintain effective risk control at every stage.

DUpdated in the execution phase

Updating risk management only in the execution phase excludes planning - where initial risk identification and response planning occur - and closing, where final risk reviews and lessons learned are conducted.

Concept tested: Iterative nature of the risk management process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management Process#Iterative Process#Project Lifecycle#Process Characteristics

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice