PMI-RMP · Question #330
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
The correct answer is A. Change management plan and lessons learned. Within organizational process assets, risk response effectiveness from past projects is most reliably found in the lessons learned database, which is also associated with historical change management documentation.
Question
Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?
Options
- AChange management plan and lessons learned
- BStakeholder register and lessons learned
- CRisk audit and lessons learned
- DRisk audit and risk matrix
How the community answered
(28 responses)- A82% (23)
- B4% (1)
- C4% (1)
- D11% (3)
Why each option
Within organizational process assets, risk response effectiveness from past projects is most reliably found in the lessons learned database, which is also associated with historical change management documentation.
Organizational process assets include historical project management artifacts and lessons learned repositories; lessons learned specifically capture the effectiveness of past risk responses, and change management records from prior projects may also document how risk-driven changes were handled, making this combination the relevant source for historical effectiveness data.
The stakeholder register documents stakeholder identification, roles, and engagement levels and does not serve as a repository for historical risk response performance from past projects.
While risk audits assess risk management effectiveness within a current project, the audit itself is not an organizational process asset repository - its findings are captured in lessons learned to become OPA.
A risk matrix is a probability-impact assessment tool used for current project risk prioritization and does not function as a historical repository of past risk response effectiveness.
Concept tested: Organizational process assets for historical risk response data
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok