PMI-RMP · Question #330

Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?

The correct answer is A. Change management plan and lessons learned. Within organizational process assets, risk response effectiveness from past projects is most reliably found in the lessons learned database, which is also associated with historical change management documentation.

Risk Monitoring and Reporting

Question

Within the organizational process assets, where would the project manager find risk response effectiveness from past projects?

Options

  • AChange management plan and lessons learned
  • BStakeholder register and lessons learned
  • CRisk audit and lessons learned
  • DRisk audit and risk matrix

How the community answered

(28 responses)
  • A
    82% (23)
  • B
    4% (1)
  • C
    4% (1)
  • D
    11% (3)

Why each option

Within organizational process assets, risk response effectiveness from past projects is most reliably found in the lessons learned database, which is also associated with historical change management documentation.

AChange management plan and lessons learnedCorrect

Organizational process assets include historical project management artifacts and lessons learned repositories; lessons learned specifically capture the effectiveness of past risk responses, and change management records from prior projects may also document how risk-driven changes were handled, making this combination the relevant source for historical effectiveness data.

BStakeholder register and lessons learned

The stakeholder register documents stakeholder identification, roles, and engagement levels and does not serve as a repository for historical risk response performance from past projects.

CRisk audit and lessons learned

While risk audits assess risk management effectiveness within a current project, the audit itself is not an organizational process asset repository - its findings are captured in lessons learned to become OPA.

DRisk audit and risk matrix

A risk matrix is a probability-impact assessment tool used for current project risk prioritization and does not function as a historical repository of past risk response effectiveness.

Concept tested: Organizational process assets for historical risk response data

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Organizational Process Assets (OPA)#Lessons Learned#Risk Response Effectiveness#Change Management Records