PK0-004 Exam Questions
1,066 real PK0-004 exam questions with expert-verified answers and explanations. Page 8 of 22.
- Question #351Project life cycle phases
A meeting has taken place with quality assurance tram members and the project manager. Which of the following events would MOST likely have triggered the meeting?
quality assuranceauditQA triggerquality management - Question #352Tools and documentation
A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:
meeting minutesaction itemschange historyproject documentation - Question #353Tools and documentation
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in t...
project charterproject management plandocument componentsWBS - Question #354Project management concepts
Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
communication methodsbusiness continuitystakeholder communicationincident response - Question #355Project life cycle phases
A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager...
tollgatephase gate reviewphase transitionquality review - Question #356Project management concepts
A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported. Which of the following is MOST...
contingency planincident responserisk responseunplanned event - Question #357Tools and documentation
As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if...
communications planmeeting managementstakeholder communicationteam coordination - Question #358Project management concepts
Two companies have merged. Which of the following may impact the project manager's communication methods after the merger?
stakeholder requirementsorganizational changecommunication methodsmerger impact - Question #359Tools and documentation
Despite receiving regular updates, a sponsor learns a project recently slipped. Which of the following documents can the sponsor review to determine the project's performance? (Sel...
status reportissue logproject performanceproject monitoring - Question #360Project life cycle phases
A new corporate policy was approved that will positively affect the project. Which of the following should the project manager do FIRST?
change managementpositive changeschedule changechange request - Question #361Tools and documentation
Given the following sprint: Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?
burndown chartsprint trackingagile metricschart selection - Question #362Tools and documentation
When developing a project schedule, which of the following tools would be MOST beneficial?
Gantt chartproject schedulingschedule development - Question #363Tools and documentation
Based on the table below: Which of the following is the critical path if Task B has extended to ten days?
critical path methodschedule calculationtask durationCPM analysis - Question #364Tools and documentation
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
RFPprocurement documentsvendor selectionrequirements - Question #365Tools and documentation
Which of the following charts is a mathematical diagram used to values for two variables for a set of data?
scatter chartdata visualizationtwo-variable analysis - Question #366Project management concepts
Expenditure tracking helps with cost:
cost reportingexpenditure trackingcost management - Question #367Project management concepts
On an OBS chart, there is a dashed line between some team members and the project manager, and there is a solid line connecting other members to the project manager. Additionally,...
OBS chartmatrix organizationorganizational structurereporting lines - Question #368Project management concepts
A project manager is determining a project's critical path to report the projected completion date to stakeholders. Which of the following information will be required? (Select two...
critical path methodtask dependenciestask durationscheduling inputs - Question #369Tools and documentation
A project manager has developed the initial schedule for an upcoming project. Using the attached schedule, which of the following is the critical path?
critical pathschedule analysisCPM calculation - Question #370Tools and documentation
A diagram or chart is required to illustrate data differences given the following: 1. The diagram or chart must track at least two variables to determine the relationship between i...
Ishikawa diagramscatter chartregression analysisquality tools - Question #371Project life cycle phases
During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship. Which of the following should t...
schedule planningtask dependenciestask durationplanning phase - Question #372Project management concepts
Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members. Which of the foll...
meeting facilitationteam communicationagenda managementteam dynamics - Question #373Project management concepts
A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding acti...
risk planningrisk probabilityrisk impactrisk response - Question #374Project management concepts
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days. Which of the following characteristics classifies this as a proj...
project characteristicstemporary endeavorproject definition - Question #375Project management concepts
Given the information in the table below, which of the following is the total project cost?
project costbudget calculationcost estimation - Question #376Project management concepts
The design team and development team disagree about what technology should be used for a major requirement. A brainstorming meeting takes place, where both teams focus on the mutua...
conflict resolutionsmoothing techniqueteam conflictstakeholder management - Question #377Project management concepts
A project manager is analyzing the cost variances produced when comparing two different projects completions. Which of the following factors could be causing the increased variance...
cost variancelabor costoverheadcost analysis - Question #378Project management concepts
One of the tasks on a project's critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive...
PMOresource managementcritical pathproject roles - Question #379Tools and documentation
A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeti...
project dashboardexecutive reportingstatus reportingstakeholder communication - Question #380Project management concepts
During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the...
change controlchange documentationstakeholder communicationchange management - Question #381Tools and documentation
A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion?
communication methodsinstant messagingteam communication - Question #382Tools and documentation
A project manager has been assigned a complex project and does not know all the activities required to complete it. Which of the following if the BEST approach to determine the wor...
WBSwork packagesbottom-up estimatingscope decomposition - Question #383Tools and documentation
A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to esca...
organizational chartmatrix organizationescalationresource management - Question #384Basics of IT and governance
The Chief Executive Officer (CEO) has changed the direction of a business and no longer needs one of the divisions. A deal is reached to sell the division to a company in another s...
demergerorganizational changebusiness change types - Question #385Project life cycle phases
The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the...
change managementscope reductiondocumentation updatechange control - Question #386Project management concepts
Which of the following describes a project's budget overrun?
budget overruncost managementproject budget - Question #387Basics of IT and governance
A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this MOST likely a result? (Choose two.)
project relocationbusiness continuityorganizational change triggersresource changes - Question #388Project management concepts
A project can be defined as:
project definitiontemporaryuniqueproject characteristics - Question #389Project management concepts
Two critical members have approached the project manager separately regarding personality conflicts. The project manager cannot remove either from the project or separate their wor...
conflict resolutionteam managementinterpersonal skillsconfrontation - Question #390Project life cycle phases
A project manager is archiving of project documents. Which of the following phases does this describe?
project closingdocument archivingproject phases - Question #391Project management concepts
Which of the following are MOST essential to developing an effective project team? (Choose two.)
team developmentskill setstrustteam building - Question #392Basics of IT and governance
A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer (CEO) directs that all meetings be conducted via video conference to save...
corporate acquisitionorganizational changehostile takeover - Question #393Tools and documentation
A company's management team is in a meeting to review all the products and services delivered in the first quarter of the year for profitability. They are requesting information on...
business caseROIpayback periodproject documentation - Question #394Project management concepts
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following sho...
change requesttriple constraintsschedule compressionchange control - Question #395Tools and documentation
A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to...
procurementvendor managementpurchase ordersphysical signature - Question #396Tools and documentation
A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week. Which of the following activi...
resource levelingschedule managementcapacity planningresource overallocation - Question #397Project management concepts
Which of the following make up a company's portfolio? (Choose two.)
portfolio managementprogramsprojectsorganizational structure - Question #398Tools and documentation
A recently added stakeholder is unaware of critical changes that will affect the department. Which of the following should the project manager do FIRST to ensure all parties have t...
communications planstakeholder managementinformation distribution - Question #399Project management concepts
A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive...
change controlstakeholder managementchange request processgovernance - Question #400Basics of IT and governance
Which of the following resources outlines consequences of non-performance?
PMOproject governancenon-performanceorganizational structure