Question
As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan. Which of the following documents should be reviewed FIRST to uncover the issue?
Options
- ACommunications plan
- BScope statement
- CProject management plan
- DOrganizational chart