As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan. Which of the following documents should be reviewed FIRST to uncover the issue?

Options

  • ACommunications plan
  • BScope statement
  • CProject management plan
  • DOrganizational chart