A project sponsor is not being updated on the project as expected. Instead of receiving information on a monthly basis, the project sponsor wants to see it biweekly and requests the use of a…

The correct answer is D. Update the project communication plan and distribute it to the stakeholders. When a stakeholder's communication preferences change, the project communication plan must be updated and redistributed to all stakeholders to reflect the new requirements.

Tools and documentation

Question

A project sponsor is not being updated on the project as expected. Instead of receiving information on a monthly basis, the project sponsor wants to see it biweekly and requests the use of a collaboration site instead of email. Which of the following actions should the project manager perform?

Options

  • AUpdate the project status report and inform the project team.
  • BUpdate the project charter and inform the project sponsor.
  • CUpdate the project management plan and review it at the next status meeting.
  • DUpdate the project communication plan and distribute it to the stakeholders.

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    14% (7)
  • C
    8% (4)
  • D
    73% (36)

Why each option

When a stakeholder's communication preferences change, the project communication plan must be updated and redistributed to all stakeholders to reflect the new requirements.

AUpdate the project status report and inform the project team.

Updating a status report addresses a single reporting instance, not the ongoing communication preferences that govern the entire project lifecycle.

BUpdate the project charter and inform the project sponsor.

The project charter defines high-level project authorization and objectives; communication preferences are not a charter element.

CUpdate the project management plan and review it at the next status meeting.

Updating the project management plan is too broad - the specific artifact to update is the communication plan, which is a subsidiary plan within it, and reviewing it only at the next status meeting delays necessary action.

DUpdate the project communication plan and distribute it to the stakeholders.Correct

The communication plan documents the what, when, how, and to whom of project communications. When the sponsor requests a change in frequency (monthly to biweekly) and channel (email to collaboration site), these are direct modifications to the communication plan. Distributing the updated plan to all stakeholders ensures everyone operates from the same communication expectations going forward.

Concept tested: Updating the project communication plan based on stakeholder needs

Source: https://www.pmi.org/pmbok-guide-standards

Topics

#communication plan#stakeholder management#communication frequency#plan updates