PK0-004 · Question #72

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?

The correct answer is B. Establish and set the baseline. Recording actual durations against a WBS requires a baseline to be set, as the baseline defines the planned start and finish dates used for comparison.

Tools and documentation

Question

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?

Options

  • AEstablish each WBS work package resource.
  • BEstablish and set the baseline.
  • CEstablish and set the quality gates.
  • DEstablish the tollgates.

How the community answered

(45 responses)
  • B
    96% (43)
  • C
    2% (1)
  • D
    2% (1)

Why each option

Recording actual durations against a WBS requires a baseline to be set, as the baseline defines the planned start and finish dates used for comparison.

AEstablish each WBS work package resource.

Establishing work package resources defines who does the work but does not create the time reference needed to compare planned versus actual durations.

BEstablish and set the baseline.Correct

Establishing and setting the baseline captures the approved, time-phased plan for each WBS work package, including estimated start and finish dates. Once the baseline is set, the project manager can record actual start and finish dates and compare them against the baseline to measure schedule variance. Without a baseline, there is no reference point against which actuals can be meaningfully tracked.

CEstablish and set the quality gates.

Quality gates are criteria used to assess deliverable quality, not schedule tracking reference points for WBS work packages.

DEstablish the tollgates.

Tollgates are stage-gate review checkpoints used for go/no-go decisions, not mechanisms for recording or comparing task-level durations.

Concept tested: Setting schedule baseline for WBS duration tracking

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#project baseline#WBS work packages#schedule tracking#actual vs estimated duration