Which of the following captures unforeseen activities throughout the project that need attention and resolution?
The correct answer is B. Action items. Action Items - A list of project actions that should be resolved in order to fulfill deliverables.
Tools and documentation
Question
Which of the following captures unforeseen activities throughout the project that need attention and resolution?
Options
- AGantt chart
- BAction items
- CProject schedule
- DMeeting minutes
How the community answered
(43 responses)- A5% (2)
- B91% (39)
- C2% (1)
- D2% (1)
Explanation
Action Items - A list of project actions that should be resolved in order to fulfill deliverables.
Topics
#action items#issue tracking#project monitoring#unforeseen activities