A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorm,TM of potential strategies. Which of the following documents should the…
The correct answer is A. Risk register. A risk register is the document used to log potential risk events and record response strategies developed through activities like brainstorming.
Question
A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorm,TM of potential strategies. Which of the following documents should the project coordinator use?
Options
- ARisk register
- BIssue log
- CCommunication plan
- DStatus report
How the community answered
(25 responses)- A92% (23)
- C4% (1)
- D4% (1)
Why each option
A risk register is the document used to log potential risk events and record response strategies developed through activities like brainstorming.
The risk register is a project artifact that captures identified risks, their likelihood and impact, and the planned strategies to address them. It serves as the central repository for all risk-related information, including output from brainstorming sessions on mitigation and contingency responses. Recording both potential events and planned strategies in one place is the defining purpose of the risk register.
An issue log tracks problems that have already occurred and are actively impacting the project, not potential future events or proactive response strategies.
A communication plan defines how project information will be distributed among stakeholders - it does not log risk events or record risk response strategies.
A status report provides a snapshot of current project health and progress, not a log of potential risk events or planned mitigation approaches.
Concept tested: Risk register purpose in risk management
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok