PK0-004 · Question #276
Which of the following would be found in a transition plan? (Select TWO).
The correct answer is C. Training requirements E. Extended support. A transition plan focuses on handing deliverables over to operations and support teams, encompassing training for end users and extended support arrangements after project closure.
Question
Which of the following would be found in a transition plan? (Select TWO).
Options
- AKey milestones
- BProject acceptance criteria
- CTraining requirements
- DTollgate approvals
- EExtended support
How the community answered
(20 responses)- A5% (1)
- C90% (18)
- D5% (1)
Why each option
A transition plan focuses on handing deliverables over to operations and support teams, encompassing training for end users and extended support arrangements after project closure.
Key milestones are found in the project schedule or project management plan, not in the transition plan.
Project acceptance criteria belong in the project scope statement or quality management plan and are used to formally accept deliverables - not a transition plan component.
Training requirements are a core element of a transition plan because end users and support staff must be prepared to operate and maintain the deliverable after handover. Extended support defines the support model, SLA, and maintenance coverage after the project team disbands, which is a defining characteristic of any transition plan.
Tollgate approvals are governance checkpoints in a phase-gate project lifecycle and are documented in the project management plan or governance framework, not the transition plan.
Extended support terms document how the solution will be maintained and supported beyond the initial delivery, which is a primary concern of the transition from project to operations.
Concept tested: Transition plan components - training and extended support