PK0-004 · Question #356
A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported. Which of the following is MOST appropriate for…
The correct answer is A. Refer to the contingency plan. When a risk event actually occurs, the project manager should refer to the contingency plan - the pre-defined, documented set of actions prepared specifically for when an identified risk materializes. A contingency plan is developed during risk planning and outlines the exact…
Question
A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported. Which of the following is MOST appropriate for the project manager to do NEXT?
Options
- ARefer to the contingency plan
- BConduct an immediate emergency team meeting
- CPerform a SWOT analysis
- DImplement the risk response plan
How the community answered
(30 responses)- A70% (21)
- B17% (5)
- C3% (1)
- D10% (3)
Explanation
When a risk event actually occurs, the project manager should refer to the contingency plan - the pre-defined, documented set of actions prepared specifically for when an identified risk materializes. A contingency plan is developed during risk planning and outlines the exact steps to take when a specific trigger event (like a fire damaging equipment) happens. It is the immediate go-to document because it avoids ad-hoc decision-making under pressure. Option B (emergency team meeting) may follow, but the first step is consulting the plan. Option C (SWOT analysis) is a planning tool, not a response tool. Option D (risk response plan) is the broader pre-mitigation strategy document; the contingency plan is the specific reactive subset of that plan activated by a trigger event.
Topics
Community Discussion
No community discussion yet for this question.