A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the…
The correct answer is C. a tollgate. A gate or tollgate is a standardized control point where the project phase is reviewed and/or audited and approved (or not) to continue with the next phase.
Project life cycle phases
Question
A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
Options
- Achange management
- BA milestone
- Ca tollgate
- Dan incident response
How the community answered
(45 responses)- B2% (1)
- C93% (42)
- D4% (2)
Explanation
A gate or tollgate is a standardized control point where the project phase is reviewed and/or audited and approved (or not) to continue with the next phase.
Topics
#tollgate#phase gate review#phase transition#quality review