PK0-004 · Question #635

The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur. Which of the following will assist the project team with building the schedule?

The correct answer is C. Task dependencies. Task dependencies define the logical relationships between tasks and are the foundational input used to sequence and time work in a project schedule.

Project life cycle phases

Question

The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur. Which of the following will assist the project team with building the schedule?

Options

  • ATask sequencing
  • BTask predecessors
  • CTask dependencies
  • DTask prioritizing

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    89% (33)
  • D
    3% (1)

Why each option

Task dependencies define the logical relationships between tasks and are the foundational input used to sequence and time work in a project schedule.

ATask sequencing

Task sequencing is the output or result of analyzing dependencies, not the input used to build the schedule in the first place.

BTask predecessors

Task predecessors are a subset of dependencies that only capture what must finish before a task starts, and do not capture the full range of dependency types needed for scheduling.

CTask dependenciesCorrect

Task dependencies identify the relationship types between tasks - such as finish-to-start, start-to-start, or finish-to-finish - which directly determine when each task can begin or end. Without mapping dependencies, the project team cannot establish a valid sequence or calculate early/late start and finish dates. Dependencies are the core scheduling input used in methods like the Critical Path Method (CPM) to build a realistic schedule.

DTask prioritizing

Task prioritizing ranks tasks by importance or urgency but does not establish the logical order or timing relationships required to build a schedule.

Concept tested: Task dependency types in schedule development

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#task dependencies#schedule development#project scheduling

Community Discussion

No community discussion yet for this question.