Which of the following is the project phase when quality assurance occurs?

The correct answer is C. Execution. Quality assurance is an active process that primarily occurs during the Execution phase, when project work is being performed and processes can be audited in real time.

Project life cycle phases

Question

Which of the following is the project phase when quality assurance occurs?

Options

  • APlanning
  • BClosing
  • CExecution
  • DScoping
  • EInitiation

How the community answered

(34 responses)
  • A
    3% (1)
  • C
    91% (31)
  • D
    6% (2)

Why each option

Quality assurance is an active process that primarily occurs during the Execution phase, when project work is being performed and processes can be audited in real time.

APlanning

Planning addresses quality planning - defining standards, metrics, and approaches - rather than actively auditing ongoing work processes.

BClosing

Closing focuses on final acceptance, handover, and project documentation, not on monitoring active execution quality.

CExecutionCorrect

Quality assurance takes place during Execution because it involves auditing active project processes and verifying that quality standards are being applied while work is underway, enabling defect prevention and process corrections before deliverables are finalized.

DScoping

Scoping defines what is included in or excluded from the project and is not concerned with monitoring execution-phase quality processes.

EInitiation

Initiation establishes the project charter and high-level authorization and does not involve quality assurance activities.

Concept tested: Quality assurance phase in project lifecycle

Topics