PK0-004 · Question #726

Which of the following is performed during the monitoring and controlling phase?

The correct answer is D. Quality assurance and governance oversight. The monitoring and controlling phase involves overseeing project performance, ensuring compliance with standards, and maintaining governance over the project's direction. Quality assurance (verifying processes are being followed) and governance oversight (reviewing project…

Project life cycle phases

Question

Which of the following is performed during the monitoring and controlling phase?

Options

  • AQuality control and training plan development
  • BCreation of schedule and fund deliverables
  • CDevelopment of transition plan and finalizing contracts
  • DQuality assurance and governance oversight

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    2% (1)
  • D
    95% (42)

Explanation

The monitoring and controlling phase involves overseeing project performance, ensuring compliance with standards, and maintaining governance over the project's direction. Quality assurance (verifying processes are being followed) and governance oversight (reviewing project decisions and controls) are both ongoing activities that span this phase. Option A is incorrect because training plan development belongs to planning/executing. Option B (creating the schedule) is a planning activity. Option C (transition plan and finalizing contracts) belongs to the closing phase.

Topics

#monitoring and controlling#quality assurance#governance oversight#project phases