Based on the table below: Which of the following is the critical path?

The correct answer is C. B, C, F, G, J, K, L, M. Build a network diagram you will arrive at the answer C. Start by adding A& B to C the result B+C = 9 which is higher than A+C = 5 . Use B + C =9 to continue building the diagram. In the end you will end with L which is dependent on I & K, the result K+L is higher than I+L…

Tools and documentation

Question

Based on the table below:

Which of the following is the critical path?

Exhibits

PK0-004 question #725 exhibit 1
PK0-004 question #725 exhibit 2
PK0-004 question #725 exhibit 3

Options

  • AA, C, F, G, J, K, L, M
  • BA, C, D, E, H, I, L, M
  • CB, C, F, G, J, K, L, M
  • DB, C, D, E, H, I, L, M

How the community answered

(50 responses)
  • A
    14% (7)
  • B
    22% (11)
  • C
    58% (29)
  • D
    6% (3)

Explanation

Build a network diagram you will arrive at the answer C. Start by adding A& B to C the result B+C = 9 which is higher than A+C = 5 . Use B + C =9 to continue building the diagram. In the end you will end with L which is dependent on I & K, the result K+L is higher than I+L therefore the path is B, C, F, G, J, K, L, M.