Question
Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?
Options
- AEmail and instant messaging to project team members and the project team members and the
- BText messages to and voice conferences with all stakeholders and project team members
- CVideo conferences with key stakeholders and the project champion
- DInstant messaging to the project coordinator and project scheduler