PK0-004 · Question #353
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter…
The correct answer is E. Measurable project objectives. A project charter document will include the following information: Project Background (Containing the business need and the reason for taking up the project) Project Objectives and Goals (Clearly defined set of objectives and goals to be achieved to fulfil the business need)…
Question
Options
- AProject title and description
- BPreassigned resources
- CBudget
- DWBS
- EMeasurable project objectives
How the community answered
(57 responses)- A16% (9)
- B5% (3)
- C2% (1)
- D4% (2)
- E74% (42)
Explanation
A project charter document will include the following information: Project Background (Containing the business need and the reason for taking up the project) Project Objectives and Goals (Clearly defined set of objectives and goals to be achieved to fulfil the business need) High level requirements High level project risks High level milestones Budgetary constraints Key stakeholders and their names Project manager’s name (Responsibility of the project manager and granted authority level for the project manager) Project Sponsor’s name Approval and signature of project sponsor