Which of the following is the burn rate of a project?
The correct answer is C. The amount of expenditures supporting the project over time. Burn rate is the rate you are spending money over time. For example, if you had a $12,000 budget and you’re spending $2,000 a month, you’ll run out of money in six months.
Project management concepts
Question
Which of the following is the burn rate of a project?
Options
- AThe amount of project staff turnover over time
- BThe positive cash flow of the project for the organization over time
- CThe amount of expenditures supporting the project over time
- DThe amount of capital spent to ensure quality of the project deliverables
How the community answered
(41 responses)- A5% (2)
- B2% (1)
- C90% (37)
- D2% (1)
Explanation
Burn rate is the rate you are spending money over time. For example, if you had a $12,000 budget and you’re spending $2,000 a month, you’ll run out of money in six months.
Topics
#burn rate#project expenditures#cost management#financial metrics