nerdexam
CompTIA

PK0-004 · Question #696

Which of the following is the burn rate of a project?

The correct answer is C. The amount of expenditures supporting the project over time. Burn rate is the rate you are spending money over time. For example, if you had a $12,000 budget and you’re spending $2,000 a month, you’ll run out of money in six months.

Project management concepts

Question

Which of the following is the burn rate of a project?

Options

  • AThe amount of project staff turnover over time
  • BThe positive cash flow of the project for the organization over time
  • CThe amount of expenditures supporting the project over time
  • DThe amount of capital spent to ensure quality of the project deliverables

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    90% (37)
  • D
    2% (1)

Explanation

Burn rate is the rate you are spending money over time. For example, if you had a $12,000 budget and you’re spending $2,000 a month, you’ll run out of money in six months.

Topics

#burn rate#project expenditures#cost management#financial metrics

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice