CompTIA
PK0-004 · Question #697
A project manager is planning a wedding that will take place during the rainy season. The possibility of rain is very high, so the project manager proposes alternatives to having an outdoor wedding…
The correct answer is A. mitigation. Mitigation is to reduce the probability or impact of a risk.
Project management concepts
Question
A project manager is planning a wedding that will take place during the rainy season. The possibility of rain is very high, so the project manager proposes alternatives to having an outdoor wedding. This is an example of:
Options
- Amitigation.
- Bacceptance.
- Cexploitation.
- Dtransference.
How the community answered
(38 responses)- A92% (35)
- B3% (1)
- D5% (2)
Explanation
Mitigation is to reduce the probability or impact of a risk.
Topics
#risk mitigation#risk response strategies#contingency planning#risk management
Community Discussion
No community discussion yet for this question.