PK0-004 · Question #488
A stakeholder wants to add four more data entry points on the accounts receivable screen of the current application being developed. Which of the following constraints would this impact directly?
The correct answer is B. Scope. Adding new data entry fields to the application is a change in the deliverable's features and functionality, which is a direct change to scope. Scope defines what is and is not included in the project. Any addition of features - no matter how small - expands the scope and…
Question
A stakeholder wants to add four more data entry points on the accounts receivable screen of the current application being developed. Which of the following constraints would this impact directly?
Options
- ARisks
- BScope
- CEnvironment
- DQuality
How the community answered
(38 responses)- A3% (1)
- B92% (35)
- C5% (2)
Explanation
Adding new data entry fields to the application is a change in the deliverable's features and functionality, which is a direct change to scope. Scope defines what is and is not included in the project. Any addition of features - no matter how small - expands the scope and should go through a formal change control process. While risks, environment, and quality could be indirectly affected downstream, the immediate and direct constraint impacted is scope.