nerdexam
ExamsPK0-004Questions#175
CompTIA

PK0-004 · Question #175

PK0-004 Question #175: Real Exam Question with Answer & Explanation

The correct answer is A: Reduced quality. Placing inexperienced interns in key project roles introduces a skills gap that most directly threatens the quality of project deliverables.

Question

A company hires a number of interns and assigns them key roles on a project. Which of the following should the project manager MOST likely anticipate?

Options

  • AReduced quality
  • BReduced scope
  • CReduced risk
  • DReduced timeline

Explanation

Placing inexperienced interns in key project roles introduces a skills gap that most directly threatens the quality of project deliverables.

Common mistakes.

  • B. Scope is determined by stakeholder requirements and the project charter, not by the experience level of the team executing the work.
  • C. Assigning inexperienced workers to critical roles increases project risk - due to higher error rates and knowledge gaps - rather than reducing it.
  • D. Less experienced team members typically take longer to complete tasks, which would more likely extend rather than reduce the project timeline.

Concept tested. Resource capability and its impact on project quality

Reference. https://www.comptia.org/training/resources/exam-objectives/comptia-project-pk0-005-exam-objectives

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice