PK0-004 · Question #176

The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?

The correct answer is A. Ahead of schedule and over budget. Anytime the SPI or CPI are below 1.0, it has a negative affect on the project. It's ahead of schedule and over budget.

Project management concepts

Question

The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?

Options

  • AAhead of schedule and over budget
  • BBehind schedule and under budget
  • CAhead of schedule and under budget
  • DBehind schedule and over budget

How the community answered

(45 responses)
  • A
    87% (39)
  • B
    4% (2)
  • C
    2% (1)
  • D
    7% (3)

Explanation

Anytime the SPI or CPI are below 1.0, it has a negative affect on the project. It's ahead of schedule and over budget.

Topics

#earned value management#SPI#CPI#schedule and cost performance

Community Discussion

No community discussion yet for this question.