CompTIA
PK0-004 · Question #177
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
The correct answer is C. Scope. It states that a non-stakeholder asks if things can be added. This would lead to scope creep since they are not going through the proper change request path.
Project management concepts
Question
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
Options
- ATime
- BSchedule
- CScope
- DCost
How the community answered
(29 responses)- A3% (1)
- B3% (1)
- C93% (27)
Explanation
It states that a non-stakeholder asks if things can be added. This would lead to scope creep since they are not going through the proper change request path.
Topics
#scope management#scope creep#constraints#change request
Community Discussion