A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?

The correct answer is C. Scope. It states that a non-stakeholder asks if things can be added. This would lead to scope creep since they are not going through the proper change request path.

Project management concepts

Question

A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?

Options

  • ATime
  • BSchedule
  • CScope
  • DCost

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    93% (27)

Explanation

It states that a non-stakeholder asks if things can be added. This would lead to scope creep since they are not going through the proper change request path.

Topics

#scope management#scope creep#constraints#change request

Community Discussion

No community discussion yet for this question.