PK0-004 · Question #178
PK0-004 Question #178: Real Exam Question with Answer & Explanation
The correct answer is A: Resource loading. Resource loading is a process used in project management that fills team members' total available time with assignments throughout a workweek. Project managers typically assign team members a percentage of a project or objective per day until they reach 100% of their weekly
Question
A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?
Options
- AResource loading
- BResource leveling
- CPrioritizing tasks
- DAllocating resources
Explanation
Resource loading is a process used in project management that fills team members' total available time with assignments throughout a workweek. Project managers typically assign team members a percentage of a project or objective per day until they reach 100% of their weekly