PK0-004 · Question #178

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

The correct answer is A. Resource loading. Resource loading is a process used in project management that fills team members' total available time with assignments throughout a workweek. Project managers typically assign team members a percentage of a project or objective per day until they reach 100% of their weekly

Project management concepts

Question

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

Options

  • AResource loading
  • BResource leveling
  • CPrioritizing tasks
  • DAllocating resources

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    8% (2)
  • C
    4% (1)
  • D
    15% (4)

Explanation

Resource loading is a process used in project management that fills team members' total available time with assignments throughout a workweek. Project managers typically assign team members a percentage of a project or objective per day until they reach 100% of their weekly

Topics

#resource loading#resource leveling#resource management#team replacement