PK0-004 · Question #178

PK0-004 Question #178: Real Exam Question with Answer & Explanation

The correct answer is A: Resource loading. Resource loading is a process used in project management that fills team members' total available time with assignments throughout a workweek. Project managers typically assign team members a percentage of a project or objective per day until they reach 100% of their weekly

Question

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

Options

  • AResource loading
  • BResource leveling
  • CPrioritizing tasks
  • DAllocating resources

Explanation

Resource loading is a process used in project management that fills team members' total available time with assignments throughout a workweek. Project managers typically assign team members a percentage of a project or objective per day until they reach 100% of their weekly