PK0-004 · Question #487
The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?
The correct answer is C. Add a new line to the communications plan to provide a weekly status report with a dashboard. Adding a new line to the communications plan to deliver a weekly status report with a dashboard is the most targeted and professional solution. It directly addresses both problems: regularity (weekly cadence) and conciseness (a dashboard format). Adding the sponsor to all…
Question
The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?
Exhibits
Options
- AAdd the project sponsor to all project email correspondence moving forward
- BInclude the project sponsor in all project meetings moving forward
- CAdd a new line to the communications plan to provide a weekly status report with a dashboard
- DInclude the project sponsor in the daily stand-up with the entire project team
How the community answered
(29 responses)- A3% (1)
- B10% (3)
- C83% (24)
- D3% (1)
Explanation
Adding a new line to the communications plan to deliver a weekly status report with a dashboard is the most targeted and professional solution. It directly addresses both problems: regularity (weekly cadence) and conciseness (a dashboard format). Adding the sponsor to all emails (A) creates information overload, not concise updates. Including them in all meetings (B) is time-consuming and not concise. Including them in daily stand-ups (D) is tactical/team-level detail inappropriate for a sponsor and still lacks conciseness.