PK0-004 · Question #486
A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the…
The correct answer is A. Regression plan. Any time of change causes a problem there should be a regression plan to revert the project back to a previous state.
Project management concepts
Question
A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?
Options
- ARegression plan
- BQuality plan
- CChange validation
- DApplication version control
How the community answered
(61 responses)- A75% (46)
- B7% (4)
- C3% (2)
- D15% (9)
Explanation
Any time of change causes a problem there should be a regression plan to revert the project back to a previous state.
Topics
#change control process#regression plan#risk mitigation#change management