PK0-004 · Question #486

A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the…

The correct answer is A. Regression plan. Any time of change causes a problem there should be a regression plan to revert the project back to a previous state.

Project management concepts

Question

A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?

Options

  • ARegression plan
  • BQuality plan
  • CChange validation
  • DApplication version control

How the community answered

(61 responses)
  • A
    75% (46)
  • B
    7% (4)
  • C
    3% (2)
  • D
    15% (9)

Explanation

Any time of change causes a problem there should be a regression plan to revert the project back to a previous state.

Topics

#change control process#regression plan#risk mitigation#change management