The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status…

The correct answer is A. Gantt chart. A Gantt chart is a bar chart that lists all project tasks, activities, and milestones along a timeline, making it ideal for showing the number of events and activities required to complete a project. A scatter chart plots correlations between two variables. A run chart tracks a…

Tools and documentation

Question

The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?

Options

  • AGantt chart
  • BScatter chart
  • CRun chart
  • DProcess diagram

How the community answered

(31 responses)
  • A
    90% (28)
  • B
    3% (1)
  • D
    6% (2)

Explanation

A Gantt chart is a bar chart that lists all project tasks, activities, and milestones along a timeline, making it ideal for showing the number of events and activities required to complete a project. A scatter chart plots correlations between two variables. A run chart tracks a metric over time. A process diagram maps a workflow or process flow. None of those alternatives show a structured list of project activities, which is exactly what a Gantt chart provides.