PK0-004 · Question #485
The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status…
The correct answer is A. Gantt chart. A Gantt chart is a bar chart that lists all project tasks, activities, and milestones along a timeline, making it ideal for showing the number of events and activities required to complete a project. A scatter chart plots correlations between two variables. A run chart tracks a…
Question
Options
- AGantt chart
- BScatter chart
- CRun chart
- DProcess diagram
How the community answered
(31 responses)- A90% (28)
- B3% (1)
- D6% (2)
Explanation
A Gantt chart is a bar chart that lists all project tasks, activities, and milestones along a timeline, making it ideal for showing the number of events and activities required to complete a project. A scatter chart plots correlations between two variables. A run chart tracks a metric over time. A process diagram maps a workflow or process flow. None of those alternatives show a structured list of project activities, which is exactly what a Gantt chart provides.
Topics
Community Discussion
No community discussion yet for this question.