nerdexam
CompTIA

PK0-004 · Question #484

A project manager is implementing a new edition of a magazine with an end-of-the-week deadline. The design analyst notices two main articles were not included, as requested by the client. Which of…

The correct answer is C. Time. Even though missing articles appear to be a scope issue, time must be considered FIRST because the end-of-week deadline is a hard constraint that determines whether any scope adjustment is even possible. Before deciding how to handle the missing articles, the team must assess…

Project management concepts

Question

A project manager is implementing a new edition of a magazine with an end-of-the-week deadline. The design analyst notices two main articles were not included, as requested by the client. Which of the following constraints should be considered FIRST?

Options

  • AScope
  • BQuality
  • CTime
  • DBudget

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    75% (27)
  • D
    17% (6)

Explanation

Even though missing articles appear to be a scope issue, time must be considered FIRST because the end-of-week deadline is a hard constraint that determines whether any scope adjustment is even possible. Before deciding how to handle the missing articles, the team must assess whether there is enough time remaining to add them without missing the deadline. Time is the binding constraint that gates all other decisions. If there is no time to add the articles, the scope conversation becomes moot.

Topics

#project constraints#triple constraint#time constraint#scope creep

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice