PK0-004 · Question #351
A meeting has taken place with quality assurance tram members and the project manager. Which of the following events would MOST likely have triggered the meeting?
The correct answer is A. Audit. Quality audits are the primary trigger for involving QA team members and the project manager in a formal meeting to assess process compliance and identify improvements.
Question
A meeting has taken place with quality assurance tram members and the project manager. Which of the following events would MOST likely have triggered the meeting?
Options
- AAudit
- BRisk register update
- CTask completion
- DResource change
How the community answered
(15 responses)- A93% (14)
- B7% (1)
Why each option
Quality audits are the primary trigger for involving QA team members and the project manager in a formal meeting to assess process compliance and identify improvements.
A quality audit is a structured, independent review of project processes and deliverables to determine whether they comply with organizational standards, policies, and the quality management plan. Audits specifically require the participation of QA team members and the project manager to review findings, discuss non-conformances, and agree on corrective actions. This makes an audit the most logical trigger for the described meeting.
A risk register update is a routine documentation activity typically handled by the project manager or risk owner and does not inherently require a meeting with QA team members.
Task completion triggers work acceptance and closeout activities, not a quality assurance meeting involving the broader QA team.
A resource change is an administrative or HR-related event handled through resource management processes, not a quality assurance function.
Concept tested: Quality audit as a QA process trigger
Source: https://www.pmi.org/learning/library/project-quality-audit-2897