PK0-004 · Question #399
PK0-004 Question #399: Real Exam Question with Answer & Explanation
The correct answer is C: Contact the key stakeholder to encourage the submission of written change requests. The project manager should first contact the key stakeholder and encourage proper submission of written change requests through the established change control process. This is the most diplomatic and process-aligned first step. Denying all requests (A) is too aggressive and bypas
Question
Options
- AHave the team members deny all change requests from this stakeholder
- BAsk the project sponsor for more funding to anticipate the change requests from the key stakeholder
- CContact the key stakeholder to encourage the submission of written change requests
- DRequest additional resources from the project team to complete the change requests from the key
Explanation
The project manager should first contact the key stakeholder and encourage proper submission of written change requests through the established change control process. This is the most diplomatic and process-aligned first step. Denying all requests (A) is too aggressive and bypasses proper evaluation. Requesting more funding (B) assumes changes will be approved before they are even submitted. Requesting additional resources (D) is premature. The correct approach preserves the relationship with a powerful stakeholder while reinforcing governance and ensuring all changes are documented, reviewed, and approved before implementation.
Community Discussion
No community discussion yet for this question.