PK0-004 · Question #400

PK0-004 Question #400: Real Exam Question with Answer & Explanation

The correct answer is D: Project management office. The Project Management Office (PMO) is the organizational body responsible for defining and maintaining project management standards, governance frameworks, and policies - including the consequences of non-performance. The PMO enforces accountability across projects and teams. Th

Question

Which of the following resources outlines consequences of non-performance?

Options

  • AProject sponsor
  • BProject team
  • CCustomer
  • DProject management office

Explanation

The Project Management Office (PMO) is the organizational body responsible for defining and maintaining project management standards, governance frameworks, and policies - including the consequences of non-performance. The PMO enforces accountability across projects and teams. The project sponsor (A) provides funding and executive backing but does not define consequences. The project team (B) executes work. The customer (C) receives deliverables. Only the PMO is structurally responsible for establishing and communicating performance standards and the repercussions for failing to meet them.

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice