CompTIA
PK0-004 · Question #778
A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST…
The correct answer is A. Timeline. Timeline - Due to employees being unable to access their accounts, this would cause a time
Basics of IT and governance
Question
A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?
Options
- ATimeline
- BQuality
- CBudget
- DScope
How the community answered
(28 responses)- A75% (21)
- B4% (1)
- C14% (4)
- D7% (2)
Explanation
Timeline - Due to employees being unable to access their accounts, this would cause a time