A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed?

Options

  • AMitigation
  • BQuantification
  • CPlanning
  • DIdentification