PK0-004 · Question #401
During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:
The correct answer is D. risk quantification. Perform Quantitative Risk Analysis uses the probability distributions to characterize the risk’s probability and impact. It also uses the project model (e.g., Schedule, cost estimate), mathematical and simulation tools to calculate the probability and impact.
Question
During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:
Options
- Arisk identification
- Brisk prioritization
- Crisk qualification
- Drisk quantification
How the community answered
(19 responses)- B5% (1)
- C5% (1)
- D89% (17)
Explanation
Perform Quantitative Risk Analysis uses the probability distributions to characterize the risk’s probability and impact. It also uses the project model (e.g., Schedule, cost estimate), mathematical and simulation tools to calculate the probability and impact.