PK0-004 · Question #379
A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too…
The correct answer is B. Project dashboard. Dashboards visually display the status of the most important elements of a project. They are typically used by executives in the organization, as they can see the most up-to-date project information at a glance.
Question
A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too long and not providing summary information on the project's progress. Which of the following should the project manager be presenting?
Options
- AProject issue
- BProject dashboard
- CProject schedule
- DProject milestone
How the community answered
(38 responses)- A5% (2)
- B89% (34)
- C3% (1)
- D3% (1)
Explanation
Dashboards visually display the status of the most important elements of a project. They are typically used by executives in the organization, as they can see the most up-to-date project information at a glance.