CompTIA
PK0-004 · Question #380
PK0-004 Question #380: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #380. The question stem and answer options stay visible for context.
Project management concepts
Question
During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints. Which of the following is the MOST likely cause of these complaints?
Options
- AThe quality of the deliverable decreased due to the rising material cost.
- BThe PM did not follow the project communication plan.
- CQuality assurance actions were not adjusted for the vendor change.
- DThe change was not documented and approved.
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#change control#change documentation#stakeholder communication#change management