CompTIA
PK0-004 · Question #364
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
The correct answer is A. RFP. An RFP is submitted when you are ready to procure and begin the work. This process includes submitting the SOW, receiving bids from vendors and suppliers, evaluating the responses, and making a selection.
Tools and documentation
Question
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
Options
- ARFP
- BRFQ
- CRFI
- DSOW
How the community answered
(44 responses)- A89% (39)
- B2% (1)
- C5% (2)
- D5% (2)
Explanation
An RFP is submitted when you are ready to procure and begin the work. This process includes submitting the SOW, receiving bids from vendors and suppliers, evaluating the responses, and making a selection.
Topics
#RFP#procurement documents#vendor selection#requirements
Community Discussion
No community discussion yet for this question.