The correct answer is A: RFP. An RFP is submitted when you are ready to procure and begin the work. This process includes submitting the SOW, receiving bids from vendors and suppliers, evaluating the responses, and making a selection.

Question

Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?

Options

  • ARFP
  • BRFQ
  • CRFI
  • DSOW

Explanation

An RFP is submitted when you are ready to procure and begin the work. This process includes submitting the SOW, receiving bids from vendors and suppliers, evaluating the responses, and making a selection.