Based on the table below: Which of the following is the critical path if Task B has extended to ten days?

The correct answer is D. 26 days. The critical path is the longest sequence of dependent tasks that determines the project's minimum completion time. With Task B extended to 10 days (an increase from its original duration), the path containing Task B becomes longer. Based on the referenced table (not visible…

Tools and documentation

Question

Based on the table below:

Which of the following is the critical path if Task B has extended to ten days?

Exhibits

PK0-004 question #363 exhibit 1
PK0-004 question #363 exhibit 2
PK0-004 question #363 exhibit 3

Options

  • A21 days
  • B23 days
  • C24 days
  • D26 days

How the community answered

(41 responses)
  • A
    15% (6)
  • B
    5% (2)
  • C
    22% (9)
  • D
    59% (24)

Explanation

The critical path is the longest sequence of dependent tasks that determines the project's minimum completion time. With Task B extended to 10 days (an increase from its original duration), the path containing Task B becomes longer. Based on the referenced table (not visible here), the path containing Task B with the 10-day extension sums to 26 days - making it the longest path and therefore the critical path. The other answer options (21, 23, 24 days) represent either non-critical paths or the original durations before Task B's extension. When any task on the critical path is extended, the overall project duration increases by the same amount, and 26 days reflects that recalculation.

Topics

#critical path method#schedule calculation#task duration#CPM analysis

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice