When developing a project schedule, which of the following tools would be MOST beneficial?

The correct answer is A. Gantt chart. The most common way to display project schedules is a Gantt chart.

Tools and documentation

Question

When developing a project schedule, which of the following tools would be MOST beneficial?

Options

  • AGantt chart
  • BNetwork diagram
  • CFishbone chart
  • DChain diagram

How the community answered

(54 responses)
  • A
    94% (51)
  • B
    2% (1)
  • C
    4% (2)

Explanation

The most common way to display project schedules is a Gantt chart.

Topics

#Gantt chart#project scheduling#schedule development