When developing a project schedule, which of the following tools would be MOST beneficial?
The correct answer is A. Gantt chart. The most common way to display project schedules is a Gantt chart.
Tools and documentation
Question
When developing a project schedule, which of the following tools would be MOST beneficial?
Options
- AGantt chart
- BNetwork diagram
- CFishbone chart
- DChain diagram
How the community answered
(54 responses)- A94% (51)
- B2% (1)
- C4% (2)
Explanation
The most common way to display project schedules is a Gantt chart.