The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the NEXT step the…
The correct answer is A. Update the documentation. Change Management Process: 2) Update Documentation 3) Analyze Impact 4) Course of action/Implementation 5) Update related plans
Project life cycle phases
Question
The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the NEXT step the project manager should take?
Options
- AUpdate the documentation.
- BImplement the change.
- CClose the project.
- DEvaluate the impact.
How the community answered
(31 responses)- A81% (25)
- B6% (2)
- C10% (3)
- D3% (1)
Explanation
Change Management Process: 2) Update Documentation 3) Analyze Impact 4) Course of action/Implementation 5) Update related plans
Topics
#change management#scope reduction#documentation update#change control